Case Study on Lean Manufacturing System Implementation in Batch Printing Industry Malaysia
1 Department of Engineering, Universiti Putra Malaysia, Malaysia
2 Department of Mechanical and Material Engineering, Universiti Tunku Abdul Rahman, Malaysia
Lean Manufacturing is a popular tool to be implemented in printing industry fields for the purpose of achieving the successful production goals and it is a well-organized method used to eliminate the waste or non-value added activities. Lean Manufacturing consists of several tools like 5S, TPM, Kanban, Kaizen and others. In this paper, the researcher is focus on TPM (Total Productive Maintenance). TPM is a concept used for maintaining plants and equipment with the involvement of all employees in the company in order to increase the overall equipment effectiveness (OEE). In this paper, the researcher will identify the problem faced in company’s production line and then implement lean tools in order to improve the productivity. Afterward, the researcher will carry out time study on company’s production line. The purpose of time study is to getting the result for OEE and the time taken for producing one piece of product. The researcher is then designed and suggested one-piece flow system to the management with showing the result on simulation that getting improvement in productivity. The result was simulated by using Flexsim and shows that 7.59 seconds was saved in producing one piece of calendar. At the end, the result shows that OEE increase from 34.3% to 60% and the company total save around 6 hours per month by implement one-piece flow. At last, by verifying the distribution of collected data, the researcher will perform Anderson Darling Normality test to ensure the distribution of data are normal.
© The Authors, published by EDP Sciences, 2016
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.