Causes of construction delay from contractors and suppliers in Thailand's oil and gas platform projects
Civil Engineering Department, Faculty of Engineering, King Mongkut's Institute of Technology Ladkrabang, Bangkok, Thailand
*
Corresponding author : gomarnp@gmail.com
Construction project delays caused by contractors and suppliers are the top problems in Thailand's oil and gas industries. Recognizing this importance and their relationships between factors can help reduce the risk of delays in construction projects. Therefore, this study set out to confirm factors and inspect relationships between delay factors of contractors and suppliers. A 16 item questionnaire survey was distributed to 134 managers, engineers, and supervisors in oil and gas platform construction projects in Thailand. A confirmatory factor analysis (CFA) was performed by the use of Amos Version 20 software program. The analysis results showed that delays caused by the contractors and suppliers had high relationships, due to high regression weighs. The delays caused by the contractors included seven factors which included poor site management and supervision (17%), lack of safety rules and regulations (16%), poor communication and coordination with others (15%), poor procurement system management (15%), defective components and mistakes during construction (14%), supplier payments lateness (13%), and poor planning and scheduling (10%). The delays caused by the suppliers included six factors which included the supply of unqualified and unskilled personnel (22%), supply of low efficiency equipment (20%), late delivery of materials and equipment (20%), supply of low quality materials (16%), late supply of workers (16%), and price escalation (5%).
© The Authors, published by EDP Sciences, 2018
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.