Case Study of Concrete Repairs on Jetty in Port Nolloth, Northern Cape
1
Aurecon South Africa (Pty) Ltd, Ports and Coastal Team, Cape Town, South Africa
2
Aurecon South Africa (Pty) Ltd, Transportation Unit, Cape Town, South Africa
3
Stellenbosch University, Civil Engineering Department, Stellenbosch, South Africa
* Corresponding author: Duan.Viljoen@aurecongroup.com
This paper describes the rehabilitation of the jetty in Port Nolloth, Northern Cape. The history of the jetty is not 100% certain, but it is believed that the previous wooden jetty was replaced by the current concrete structure towards the late 1940’s. There were no as-built drawings of the jetty structure available. The jetty was in a deteriorated state and required a very thorough forensic investigation to determine the state of deterioration and to develop a design for the rehabilitation thereof. The forensic study, conducted by a specialist sub-contractor, included ferro-scanning (steel reinforcement number and spacing), core samples, non-destructive testing on the structure and visual inspections. From the investigation it was found that the concrete used for the jetty is generally of good quality (high strength, good compaction, and good aggregate distribution) and cover depths are in most locations in excess of 40 mm. However, after 60 years of marine exposure the structure suffers from very high chloride contamination and severe rebar corrosion damage. Previous repairs were found to generally have failed to offer any noteworthy protection to the structure. Large cracks, spalled concrete and exposed corroded steel reinforcement were evidence of the chloride contamination. A structural analysis to verify the jetty capacity was also completed and it was found that it is imperative that the original cross-sectional area of the piles is restored. The methods proposed and employed to rehabilitate the jetty were patch repair (trowel applied concrete and sprayed concrete), sectional casting of concrete (with formwork), and replacement of reinforcement. The work commenced mid-2016 and was substantially completed end of 2017.
© The Authors, published by EDP Sciences, 2018
This is an open access article distributed under the terms of the Creative Commons Attribution License 4.0 (http://creativecommons.org/licenses/by/4.0), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.