Challenges faced for micro-tunelling works in Jadaf, Dubai for long drive on large scale projects (case study)
1 Project Director; Gulf Petrochemical Services and Trading L.L.C (Dubai Br)
2 Managing Director; International Foundation Group L.L.C
3 Professor, Water and Environmental Engineering; Heriot Watt University (Dubai-campus)
* Corresponding author: harshlovely@hotmail.com
This paper presents the challenges faced during micro-tunnelling process in Emirates of Dubai. In permeable grounds, the loss of slurry increases the cutter head torque and reduces penetration rates. Overcut is formed to provide space for converging ground and enables the evenly circulation of lubricant flow on the pipe line, as such buoyancy effects of fluid lubrication act on the pipe to lessen the drag during jacking. Micro-tunnelling techniques are used to reduce penetration resistance within the pipe string by providing sufficient uniform overcut and continuously injecting polymer lubricants. It is also observed that as the Urban area in Dubai is surrounded by built structures and numerous underground services, a special consideration is required to protect these services especially DEWA ED Cables. Also, the high ground water table, fractures within the rock and proximity of creek makes things very difficult to reduce the water table level in launching / receiving Pit and have difficulties in breaking the hard ground within the Pit. At Wafi Interchange, proposed development for the extension of interchange had to be incorporated in the alignment and accordingly standard pipe fittings to be introduced in the alignment. There are services towards Sheikh Butti palace (launching pit side) and on the other side (receiving pit). Ongoing construction of Al Jaliliya children’s hospital requires close coordination and safety related issues to be addressed prior to mobilization of heavy equipment at the proposed micro-tunnelling area. The receiving pit at Emarat petrol pump was also critical and special approval from RTA is required to close one lane at the heavy traffic along the service road, parallel to sheikh Rashid road. The removal of ground water was another challenge because near Sheikh Butti palace the drainage network was not completed and hence special arrangement was to be made to discharge the water near the creek, for which DM environment approval are to be sought.
© The Authors, published by EDP Sciences, 2017
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.