Evaluating social infrastructure financial feasibility with life cycle costing methods
Department of Civil Engineering, Universitas Pancasila, Jakarta, Indonesia
Social infrastructure is defining as a physical facility that has been build for local community provided by government, private, or even from other institution. Social infrastructure dedicated to a function of place, for a particular group of people or those with special needs. The social infrastructure concept that will be discussed in this research is Road Side Station, adopted from Japanesse Michinoeki. Similar with michinoeki, the road side station is predefined to organize service functions to road users, economic empowerment of local community, and part of incubation service for its surrounding area. Diffrent from highway’s rest area that located at highway (toll road), the road side station will be located at nation road’s side. In 2016, the Ministry of Public Works dan Housing developing a pilot project of road side station located in Tugu, Trenggalek District, East Java Province. According to that, this research is aim to analyze a model for evaluating social infrastructure financial feasibility, based on case study in Tugu’s Road Side Station. This research used quantitative approach and then the Life Cycle Costing (LCC) methods will analyze and evaluate the financial modelling from construction phase to operating. With LCC methods, the percentage of Operation and Maintenance Cost (OM Cost) from all of the Capital Expenditure Cost (CAPEX Cost) can be calculate. Finally, the result shows that developing and operating Tugu’s road side station through out its life cycle is financially feasible, according to the LCC analyze.
© Owned by the authors, published by EDP Sciences, 2012
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.