Investigation on pile-soil-tunnel interaction due to adjacent loaded pile row by 3D FEM
1
Faculty of Engineering, King Mongkut’s Institute of Technology Ladkrabang, Bangkok, Thailand
2
Faculty of Engineering, King Mongkut’s University of Technology Thonburi, Bangkok, Thailand
*
Corresponding author : narunat2835@gmail.com
The effect of adjacent loaded pile row on the existing tunnel is analysed by 3D finite element method. The MRTA project is used as reference case in this study. The case study is divided into two cases, tunnel and pile tip located in soft clay and stiff clay, respectively. The pile diameter of 1 m and pile tip located at the elevation of tunnel crown with various number of piles within the row were considered. The analysis results are shown in terms of total soil displacement (without tunnel) and maximum tunnel deformations. Both total soil displacements and tunnel deformation increase with the number of piles and approach a maximum value when the number of piles is greater than 13 and 11 for cases tunnel in soft and stiff clay, respectively. This reveals that the tunnel deformation mechanism is primarily due to the soil displacement.
© The Authors, published by EDP Sciences, 2018
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.